Hi Team,
I am working for a client where GRC 5.3 is implemented.
We have 5 weekly incremental Periodic job scheduled in RAR . Those have been scheduled at the time of implementation by a different person.
Now I want to know the last run Date or till which date the job will be running. Accordingly we need to reschedule that.
But I am not able to find the Last run date/ End date of those periodic scheduled job.
I will be helpful if anyone provide me update on that.
you can see the details in job history. If you have set java logger in configuration then you can view log for the job in RAR itself. You can also disable a job in RAR.
HI ,
I have checked in "Show Job Histry" button , but it shows that details of dates it already run till date. It does not show till what date it is supposed to run periodically. Also " view Log " button is disabled in our system.